1.Renovation Works Arab Bank Al Salam Branch 2.Refurbishment of Al- Bireh WWTP – Contract 1 3.Construction Works for Bethany Branch (Renovation Works) 4.The New Building for A.M QattanFoundation Site Clearance and Enabling Works Package(AMQ-EWP-2013)
![post](http://osaily.com/portal/wp-content/uploads/2015/11/kk-680x400.jpg)
Nablus Waste Water Plant Project
Nablus Waste Water Plant Project (WWTP) in Nablus City Was handed Over on 08/07/2013 ; The project financed by KFW Implemented by Osaily Trading Contracting Co. & KPR ” Kinetics & Passavant Roedgir- Germany”
![post](http://osaily.com/portal/wp-content/uploads/2015/11/nn.jpg)
Poured the Concrete for Foundation of the Aeration Tank
On 04/10/2011, The Company Poured the Concrete for Foundation of the Aeration Tank at NWWTP Quantity of Concrete : 1350m³ Steel Reinforcement :300 Tons Area of Tank : 3700m² The Operation Started 4:00am till 12:00pm
![post](http://osaily.com/portal/wp-content/uploads/2015/11/page24-122.jpg)
Excavation Works Started at Waste water Treatment Plant Project in Nablus.
Excavation Works Started at Waste water Treatment Plant Project in Nablus. On November. 2010 Osaily Trading Contracting Co. signed a contract with” KINETICS GERMANY to Implement Nablus Waste Water Plant Project The Project is financed by KFW & Expected to be finalized in Year 2012. Nablus Waste Water Plant Project.pdf
![post](http://osaily.com/portal/wp-content/uploads/2015/11/Telecontrol2.jpg)
Osaily Trading Contracting Co. Handed over
Osaily Trading Contracting Co. Handed over : ” Telecontrol System for Hebron Water Network Project ” on November. 2010
![post](http://osaily.com/portal/wp-content/uploads/2015/11/news2.jpg)
Osaily & IRD Handed over USAID schools projects
Osaily & IRD Handed over USAID schools projects on: 16/8/2009. – Kraisa School – Dura / Hebron – Tarqumia School- Tarqumia / Hebron – Gheit “Al Quds” School / Hebron